Work at the
low energy stage of REX-ISOLDE
Shutdown - year 2004-2005
Action Time Responsible Date
Vacuum group
Find air leak in REX system 2
days vacuum group before 15/3
Find
leak near TH-T1C, at the exhaust port of the turbo in the TRAP section
½
day vacuum group before 15/2
Dismount
and send away 180 l/s collector turbo for revision Done
½
day Fredrik + S. Meunier
HT
lens interlock in EBIS 2
hours Fredrik + David P before 1/3
Turbo
pump revision S.
Meunier before
1/3
Bakeout zeolithe trap ½ day vacuum group before 15/3
Repair/exchange EBIS collector Penning gauge Done
1
day Fredrik
Connect the fast shutting valve at the REXEBIS to the
Simatics system before
1/3
1
day D. Porret
Bakeout the EBIS 1 week S. Blanchard before 15/3
Bakeout the REX mass separator 1 week S. Blanchard before
15/3
Exchange copper for silver seals 3 days technician
+ vacuum group before 1/3
Repair turbo pump controller for 180 l/s pump at EBIS
2
days D. Porret before 1/3
Manufacture
drift tube sleeve 1 day technician before 15/2
Test
current integrator box for pulsed beams
1 day Fredrik +
operator low prio.
Dismantle
REXEBIS + magnet 1 week Fredrik + Richard Nov
Repair
REXEBIS SC 1
week external firm + Fredrik Dec
Cool
down REXEBIS and test 1
week technician + Fredrik Dec
Cool
down and map EBIS magnetic field
2
weeks technician + Fredrik Jan
Repair
EBIS extractor 1 and 2, align 1 weeks technician
+ Fredrik Jan
Re-install
the EBIS 3
weeks technician
+ Fredrik Feb
High
water pressure in cooling water line
1 day Fredrik +
Thomas S low prio.
Design
support, manufacture and install telescope for the EBIS after 1/4
1
week techn
+ Erwin/align. group + Fredrik
Install
recovery line for LHe at REXTRAP before
15/2
½ day technician
Install
and test power regulation for REXTRAP ion source before 15/2
2
days technician + Pierre + M.
O’neil
Install
and modify (Al foil + modification of holder) PM tube at REX mass sep before
15/2
4 days workshop
+ Fredrik + Georgi
Cool
down EBIS for April run 1
week technician + Fredrik end March
Startup
EBIS for April run 2
weeks operator + Fredrik April
Test Li/Cs production in REXTRAP ion source
1
week Pierre + technician +
operator March
Repair
movement for REXTRAP injection plate before
15/2
1
day technician + control
engineer
Clean the trap and EBIS cages 1 day technician before 15/3
Motor generator revision 3 days C.
Mastrostefano before
1/3
Build up electron cathode test stand 1 month PhD
+ techn. + Fredrik low
prio.
Test cathodes 1 month Fredrik ????
Exchange cooling tubes for EBIS 1 day C. Mastrostefano before 1/3
Clean flow meters for water cooling at EBIS before
1/3
½
day C. Mastrostefano
Completely new (and reliable) interlock system for
baking, pumps, HV and cathode heating
4 weeks technician low prio.
Construction, installation and test of power control
for the cathode heater before
1/3
2
weeks M. O’neil
and Fredrik
Produce 2 Macor insulation
pieces 1 day C. Mastrostefano before 15/2
Misc construction jobs 3
days C. Mastrostefano Dec-Mar
AB/PO
Implement
vacuum interlocks for HT supply in mass separator and BTS
1
week? N. David before 1/4
Arrange
adaption cable for FUG 60 kV exchange to TREK supply
1
day N .
David before
1/4
Implement
slow extraction out of the EBIS
2
weeks Joakim
Cederkall before
1/4
Install
new control system for REXTRAP before
1/4
4 week Romain +
Exchange
REXTRAP control computers 2 days Romain S Done
BDI
Install
and test
3 days technician + Fredrik
Misc
LN2 filling of REXTRAP over Christmas
Once
a week C. Yazidjian
Possibly
this shut down
Shield REXTRAP roughing pumps? 1 week radioprotection
Connect REXTRAP roughing pumps to recovery balloon?
?
weeks vacuum
group
Time
schedule
Magnet repair and first cooling down in Dec
Second cooling down and magnetic field alignment Jan
Re-installation March or April
Startup beginning or end of
April depending on degree of involvement in the LHC-
Protons to ISOLDE 21st of April
Tests at the
low energy stage of REX-ISOLDE
Shutdown - year 2004-2005
I.
On
line tests – new ion source or separator
Light
masses, injection and cooling, breeding.
Ø
Li
cooling, breeding.
Goal: Refining the injection into the EBIS for light masses. Check-up of the timings.
Scheduled: Before 1/5 – 1 to 2 weeks - Pierre and Fredrik
Ø
He
cooling, breeding.
Goal: same than before + overcoming the charge exchange problem inside the
trap. Testing other cooling method or H2 cooling?
Scheduled: Low priority since no proposal yet. Possibly during the second offline period – 1 week to 1 month with
4 days on line. Pierre & Fredrik + stagiaire?
Heavy
masses, breeding tests.
Ø Pb cooling, breeding.
Goal: refining the breeding for heavy masses/defavorable
A/Q. Tests of long breeding times together with long trapping cycle. Cs could
be used from the current ion source.
Scheduled: Second offline period. 3 - 5 days on
line. Fredrik & Pierre & Richard
Noble
gases, trapping tests.
Ø He,Ne,Kr,Ar,Xe trapping.
Goal: cooling tests with He as a buffer gas. Ions lifetime measurement. He cooling
again. Check up of the impurities inside the trap.
Scheduled: Second offline period or
before if new ion source. Low priority for operation.
2 days on line plus 1 month analysis, calculation, theoretical investigation.
Mass
resolving power tests.
Ø Some isobar rich beam, "cocktail"
beam.
Goal: mass resolving power tests at the trap
Scheduled: Second offline period. 3 - 7 days on
line. 3 – 4 months of a training period of a stagiaire.
Stagiaire + Pierre
II.
Off
line tests, technical improvements
Test if EBIS
injection efficiency for 30 and 60 keV is similar
Scheduled: 3 days Fredrik + Pierre + operator(?)
Before 1/5
Test
rotating wall cooling and injection into EBIS with very high current beams
Scheduled: 1 week Pierre + Fredrik. Before 1/4
New ion
source
Scheduled: 2 months Pierre + Technician. before 1/3
Remark: depends on the results obtained with the ISOLTRAP ion source.
Provide beam for Witch
Scheduled: 4 - 6 weeks in total. Operator(?)
Or Witch team (
REX
LINAC and Separator 2004/2005 shutdown work
latest date
Vacuum:
-
Replacement of all Pirani gauges at the Cavities 01.02.
(Porret)
-
Improvement of automatic controls
for the whole system 01.03.
(Porret)
-
Improvement of vacuum in the
Separator 01.02.
(Sieber, Wenander)
-
Vacuum interlock for high voltage
cassettes in separator 01.04.
(Porret, David)
-
Valve of 0° beamline
in automatic system 01.04.
(Porret)
-
Repair of Penning gauge in sect. 5 01.02.
(Porret)
Power
supplies:
-
Replacement of old Danfysik Power Supply (Ben.MQ10…) 01.01.
(David,
Sieber)
-
Installation of 3rd
(David,
Deloose)
-
Recabling
of Heinzinger HV casettes 15.03.
(David,
Ext.)
-
Vacuum interlock for high voltage
cassettes in separator 01.04.
(David,
Porret)
-
Change of polarity in 7-gap sect. 01.03.
(Sieber, David)
-
Repair of phase detectors of several
Danfysik PS 01.03.
(David)
Rf-
system:
-
Renovation of ventilation system
amplifier room 01.02.
(Sieber)
-
Rearrangement of 200 MHz low level
rack 01.02.
(Broere, Hajdas, Marques, Ext.)
-
Test of 100 MHz high res. Phase
shifters 01.04.
(Neville,
Broere)
-
Repair of 200 MHz high res. Phase
shifter 01.02.
(Neville,
Broere)
-
Production and test of 8 fast ampl. And phase modulators 01.06.
(Neville)
-
Installation of independent phase
measurement 01.04.
(Broere, Neville)
-
Improvement of timing for the
amplifiers 01.12.
(Neville)
-
Production of spare anode capacitor
200 MHz (
(Kester)
-
Test of MPI bus connection to BERTRONIX Simatic 01.05.
(Marques)
-
Cabling work for timing signals at
one oscilloscope 01.04.
(Broere, FSU)
-
Production of rails for dismounting
of 100 MHz rf cavity 01.02.
(Broere, workshop rf-group)
-
Improvement of outcoupling
from 7-gap 2 amp. cavity 01.03.
(Broere, Hajdas)
-
Repair of RFQ Dressler
Preamp 01.03.
(Broere)
-
Repair of 200 MHz amplifier 01.02.
(BERTRONIX,
Broere)
-
Installation of grid1 rf-filters at 100 MHz systems 01.04.
(BERTRONIX,
Broere)
-
Reinstallation of the original 200
MHz anode rf-filter 01.04.
(BERTRONIX,
Broere)
-
Improvement of 100 MHz grid1
switching modules 01.04.
(BERTRONIX,
Broere)
-
Achieve 100 Hz operation of the linac 01.04.
(BERTRONIX,
Broere)
- Repair of old Fast Ampl.
and Phase Mod. 01.01.
(Kester, Hegewisch)
- Remote Control application for rf-amplifiers 01.05.
(Deloose, Marques, Sieber)
Other
activities:
-
Realignment of 2. beamline 01.04.
(Sieber)
-
Improvement of REX cooling water
pressure 01.04.
(Sieber, Wenander)
-
Reinstallation of winXP on BD FEC 01.01.
(Deloose)
-
Built up 20 kV
test stand for linac test source in bdg. 275 01.04.
(Sieber)
-
Beam tests with changed polarity of
7-gap lenses 01.05.
(Sieber)
-
Emittance measurements at IH 9-gap 01.05.
(Sieber)