Minutes from REX meeting 2005-09-23
Present:
General
* The beryllium run (isotopes 12 and 11) went
very well. A summary is attached to these minutes.
* The
krypton run (isotopes 88 and 92) went well. A summary is attached to these
minutes.
* Xenon
138, 140 and 142 have been delivered to the experiment. A summary will come
with the next minutes. The transmission from
* Romain was not accepted as a
* Fredrik
will update the spending figures for 2005 together with Didier and Mats next
week.
* David Porret will be asked to come over and start implementing
the last vacuum elements into the Simatics
* It was
decided that an extra run for REX will be scheduled. Between Thursday evening
26/10 and 1/11 9Li should be delivered to the second beam line. Didier and Hans
Broere are however away so we are hoping for a well
behaved linac.
* Didier
will be away from 29/10 to 2/11.
* Mats
presented a status report of the ISOLDE and REX-ISOLDE control system at the
AB/CO review meeting. He underlined the necessity of having a coordinator for
all control system activities at
TRAP and EBIS
* The
main control computer for the REXTRAP CS has now been running uninterrupted for
three weeks.
* Bugs in
the scanning interface for the REXTRAP CS will be corrected for next week.
* Sylvestre Catin will come next
week and install extra memory for some of CS computers.
* Nicolas
David would like to measure the capacitance of the excitation electrodes in the
trap during next week.
* A test
confirmed that the injection efficiency into the EBIS is maximal at an electron
beam current of 190 mA and decreases for higher
currents even if the injection optics is retuned. This is undesirable as
heavier charge bred ions will require a higher electron beam current. Dedicated
tests with higher currents have to be carried out after the Zn run.
* For the
next Li or Be run we could imagine injecting He gas
into the EBIS to make use of the ion-ion cooling effect. This would however
need some testing before.
LINAC
* The 9-gap amplifier is now operational and Xe is presently accelerated to 2.85 MeV/u.
The operation frequency is 5 Hz but could be increased. The amplifier can
deliver 90-93 kW. However, the amplifier still trips occasionally. The tuning
controller was faulty and causing instabilities. It has been replaced by a
temporary one.
* Before the Li run at 50 Hz the 9-gap cavity
has to be slowly conditioned for this higher power a week or more in advance.
* 100 Hz operation can not be performed
before a new transformer is installed in 7-gap 3 amplifier.
* As higher power levels can now be reached
in the 9-gap (in principle 100kW / 0.1duty cycle) the Safety Commission should monitor
the x-ray along the linac and if necessary install
warning signals.
* It was difficult to obtain a nice beam spot
at the Miniball PPAC when using the 9-gap. The
question of a proper functioning of the PPAC was raised. Test with stable beams
next week are foreseen.
* The general application window for the current
(visual basic) control application of the Linac beam
optics needs modifications. New elements should be added and the readback feature implemented for the program to be useful.
Didier will speak to Nikolai about these issues (keeping in mind a new
application will be available next year).
Minutes taken by Fredrik Wenander