Minutes
from REX meeting 2005-06-16
Present: Mats Lindroos (chair), Fredrik Wenander, Georgi
Georgiev, Nikolai Trofimov
and Pierre Delahaye
General
*
The minutes from the last week were approved.
*
The 70Se run finished on Monday evening. The users were overall content. A
performance report of the run is found in a separate document on this page.
*
David Porret will be invited for the next meeting to
report on the consolidation progress and the implementation of the vacuum
system into the control system.
*
There are two candidates for the short term replacement of Thomas Sieber when he departs.
* Georgi inquired about the breakdowns of power supplies in
the Linac line during the run and what is done to
prevent similar incidents in the future. Nicolas David is presently revising
all the supplies and improving their connections.
* Georgi will move the ionization chamber from the second to
the straight beam line. Thus it can be constantly installed without interfering
with other setups in the second beam line.
Thomas
is absent from 16/6 until 4/7 (incl)
Fredrik
is absent from 18/6 until 29/6 (incl)
REXTRAP and REXEBIS
*
The target group has been asked to add Rb as surface
mass marker in the two coming targets for the Ni/Cu and Sn
runs, on top of the Ni, Cu, and Sn mass markers for
the lasers.
*
Profile pictures of the beam in the BTS should be taken using the MCPs. This will act as reference for future ion injection
into the EBIS this year.
* The
recently noted high trap efficiency (>50%) should be verified with careful
measurements and
*
The REXTRAP GUI should be let running continuously with different operation
conditions (scope, picoamp, dummy etc) to see what
provokes the crashes so this can be avoided in the future. Romain
should start the development of a new GUI asap.
* Romain and Nicolas David will improve the correspondence of
the set and readback values in the control programme for the BTS section.
* Romain will look into why the readback
values of the REXTRAP HT are jumping in time.
*
The emittance meter is being dismantled and shipped back to LMU.
*
One of
*
The EBIS motor-generator will be stopped in August for investigation of the
starting up problems.
*
The ‘
*
The weak signal in RFQ.BO30 was due to a misalignment of the insertable Al plate into the beam. The chamber has now been
rotated and the MCP response is improved significantly. The correct voltages
are: MCP gain 1800 V; Acceleration potential 3500 V; Phosphor voltage 4000 V.
*
The readout of BTS.FC150 and SEP.FC80 are still unstable for high currents
(>1 nA). Mats has been asked to contact Enrico
Bravin from the BD group about the problem.
LINAC
*
The plans for the work on the rf-system while Thomas
is away are the following:
-
The high voltage transformer from the RFQ amplifier will be removed this week
and shipped back to
-
One of the two modified HV trafos will be installed
before the next REX run
-
Additional measurements will be done next week to find the reason for the
permanent reflections from the cavity. Besides this, the amplifier has to be
made less sensitive to short peaks in the reflected power signal. Han will discuss
with Berdermann if one can install a "pulse
reduction" for this. It exists in Linac3, so it should be feasible at REX
as well.
- At
the same time he will discuss the possibility to send the 200 MHz amplifier
back to
- We
found that we have to buy one additional oscilloscope (5kCHF) on the REX budget
- If
the problem with the reflected power is once solved, there might be another
series of measurements on the dummy load (with the 200 MHz) in the week after
next week
to
determine the maximum duty cycle (which is, as you know, limited by the heating
problem). At the moment, anything higher than 20 Hz, 500 us at 90 kW results in
switch offs each 1-2 hours.
-
-
There is still air coming out at the ventilation system in the amp room,
although they said they closed the slots. It might be the best if the rf-workshop simply produces some sheets to close them once
for all (except 2 of them).
* The slow pumping
down of the RFQ section could maybe be due to air pockets in one of the
quadrupole lenses in front of the RFQ cavity. The drawings should be
investigated and possibly the section being opened up during next shutdown for
optical inspection.
Controls system etc
*
The beam diagnostics FEC has been working satisfyingly since the complete
reinstallation of the software last Friday. Sylvestre
Catin has been asked to look into some still
remaining network problems on the console computers in the control room.
*
Nikolai T will carry out some tests with the new PLCs
for the beam optics control during this micro shutdown. Thereafter he will test
the new controls for the RF.
*
Mats has contacted an external programmer to
investigate if he could implement the slow extraction of ions from the EBIS.
The work should be supervised by Joakim Cederkall. Fredrik pointed out that it is not only a question
of programming but also work with the hardware to find the problems with the
jittering timing and the malfunctioning vector writing to the GFAS timing
modules. This programmer could possibly also do the application programmes for the new control system.
Minutes
taken by Fredrik Wenander