Minutes
from REX meeting 2005-02-09
Present: Pierre Delahaye, Mats Lindroos (chair),
Luis Fraile, Fredrik Wenander, Romain
Savreux, Nikolai Trofimov
General issues
* The Miniball steering
committee will decide when Miniball can be
operational at ISOLDE, the tentative date is mid May.
* A
technical stop of 1-2 weeks for REX-ISOLDE is planned in June/July for the
implementation of the new control system for the Linac.
The time needed is mainly dependent on the installation work required by the
*
Luis requested input from the REX team concerning what development and tests
that are needed for the beams to be scheduled this year. Some difficult beams
were identified, such as: Se (molecular beam with high contamination), 138Xe
(long breeding time), 11Li and 11Be (lifetime, cooling and injection
efficiencies and contamination from the EBIS). If possible these should be
tested in advance.
*
The informal beam inquiry from Bo Cederwall in KTH,
*
Fredrik should contact Joakim Cederkall
concerning his suggestion to support with mass resolution tests in the REXTRAP
and take care of the commissioning of a beta detector and possibly installation
of a tape state after the EBIS.
*
Maria Jose Garcia Borge has been informed about the
development plans for the 11Li beam. If possible the REXTRAP will try to
increase the cooling efficiency using Ar as buffer
gas. Thomas Sieber says that 100 Hz operation of the linac can be possible earliest in June, more realistic in
July/August.
*
The AB/CO group has arrange an industrial support contract for the REX PCs. The
person in charge is Sylvester Catin. Mats has also agreed to pay Ivan Deloose
2-3 hours to introduce him to the ‘old’ control system.
*
The manpower needed to write the application programmes
for the new control system is not solved, and no easy solution is at hand. From
the 1/10-2005 some support could come from the OP group, but Nikolai pointed
out that the need is immediate. He also underlined the need for continued
maintenance and support, over a longer time period than 2 years.
*
One REX PC was brought to the PC shop with broken power supply.
* An updated
version of the REX homepage is soon to be launched.
Comments to its content and layout are still welcome to Fredrik.
REXTRAP and REXEBIS
* The
* Romain Savreux is continuing
working on the REXTRAP control system. The system will be tested during the
emittance measurements foreseen for the next couple of weeks.
* A power
regulation unit for the oven has been built by Michael O’neil.
It should keep the emitted current from the local trap ion source constant. The
evaluation will take place during the emittance measurements.
* The oil for the
REXTRAP roughing pumps will be changed on Thursday. Also for
the REXEBIS.
* A solution for
the modification of the REXEBIS collector cross is found. The alignment should
be finished this week.
* The cooling
tube inside the EBIS bore was deformed. The reason could be ice building up due
to insufficient water flow. The tube had to be cut up and removed and the
baking band and insulation redone. A new cooling tube was rapidly produced and
sent by
* The B-field
alignment of the EBIS has been time-consuming and difficult. The straightness
reached previously can not be repeated, it is approximately a factor 2-3 times
worse. If this affects the performance of the electron beam is difficult to
answer. Richard Scrivens has spent a significant
amount on time on this together with Fredrik.
* An inquiry to
the different support groups about the progress of the shut-down work for the
low-energy part of REX was launched. The AB/PO is ahead of schedule, while
other groups still have to start their tasks.
* There will be
no LHe delivery between the 23/2 and the 28/3. That
means the EBIS has unfortunately to be warmed up during that time, and 4 days
of cooling down time has to be added.
* A diploma
student, Klaus Allinger from LMU Munich, will come to
* Richard Scrivens will be asked to supervise the shutdown work while
Fredrik is absent.
LINAC
* 100 Hz operation can be
possible earliest in June. More realistic July/August (perhaps after the break
we plan to have for LE lenses controls tests).
* The 200 MHz system is now
in
* 4 spare MCPs
are back from repair. They will be in the rf-cupboard.
*
Next meeting will
take place
Minutes
taken by Fredrik Wenander