Minutes from REX integration meeting 11/2/2004

 

Present: Friedhelm Ames, Pierre Delahaye, Fredrik Wenander, Mats Lindroos, Peter Butler, Luis Fraille, Lee Neville

 

 

First the new RF technician Lee Neville was welcomed to the team.

 

 

1. Miniball meeting

At the Miniball meeting in Leuven beginning of Feb 2004, the user’s main requests were:

* Higher final beam energy (the upgrade to 3 MeV/u is welcome)

* Longer pulse duration from the EBIS. Slow extraction should be implemented. A matter of reprogramming the ramping of the trapping tubes.

* Phil Woods inquired about the AlF tests. Mats Lindroos will contact him when ISOLDE and REX are ready.

 

 

2. Control system

* O. Kester has been in contact with Mats Lindroos concerning sending Stephan Emhofer to CERN in beginning of April to be involved in the re-writing of the control system. The financing remains to be clarified.

* A technical meeting with the people involved with the control system was held in the beginning of the week. The technical solution for upgrading from NT to XP exists. A framegrabber card for the BD computer has to be changed. One would then run XP to 2006. The computers concerned are the BD, Profibus FE, linac, EBIS, control room computers.

* The non-working PCs in the control room have been emptied from useful insert cards (potentiometer card etc) and recuperated by the IT department.

* A request for a 20 inch screen has been sent to Philippe Potdevin as no spare screens were available from the ISOLDE controls.

 

 

3. REXTRAP

* The trap delivered stable beam to WITCH last week. At the end of the run no ions were extracted from the ions source any longer. It has been refilled and some missing dimensions were retrieved when the source was opened. The remote control of the gas has been repaired and tested.

* Next week beam transfer line tests to the EBIS are foreseen. Ivan Podadera will be invited.

* The preparation for the emittance measurements have started. The emittance meter will be requested for test in March. Friedhelm Ames will contact Munich.

 

 

4. REXEBIS

* The turbo pumps are under revision. The 2 double stage molecular drag pumps are damaged (vibrating and blocking, respectively), possibly by overheating. One could be repaired, the other not. A replace pump of same type would cost 22 kCHF, so a cheaper and less performing pump will be bought instead. Delivery mid March. Small Alcatel pump still to be revised.

* The gun gate valve was found to be scratch at the sealing. Sent away for re-machining.

* Section 0 can now be pumped again after the fast-shutting valve is permanently connected to a gas bottle.

* The unwanted switching-off (two times) of the controller for the electric bender turbo in the separator is probably caused by problems in the mains line. David Porret is looking into the issue.

* A spare collector supply, also to be used at the test bench and for higher electron currents, will be ordered. An additional expense to the budget of 8400 euro.

* The alignment of the drift-tube is still pending.

* A number of smaller jobs under progress.

* A scintillator with PM-tube is under installation at the dipole magnet in the separator line. Ideas about a Si-detector after the trap (at WITCH) are being considered.

 

 

5. Linac

* The cost for the repair of the Coulotron MCP is lower than expected. So also the cost for the cabling and ventilation work for the 200 MHz amplifiers.

* The energies after the upgrade were clarified. Maximal energy will be 3 MeV/u. There is a discrete step from 2.3 to 3 MeV/u. 3.1 MeV/u is not reached as the energy spread into the new 9-gap resonator is too large for the then required 2.3 MeV/u injected beam.

* Misc installation works are on-going in the hall. Tests of the RFQ.BO30 MSP suggest it is broken. It has been exchanged for a MCP.

 

 

6. Schedule

* The startup date of REX is still foreseen for the end of March.

* A few on-line requests were mentioned: 28Mg, 24Na, 66Ni, 68Ni, Se. Highest priority have AlF and elements around mass 140 (D. Habs experiment).

* 7 Miniball experiments are to be scheduled from July to October.

* For future Kr runs (and noble gas runs in general with high production rate):

     1. The trap efficiency has to be optimised.

     2. The trap roughing pumps have to be shielded or the area surveyed (A. Dorsival contacted about the matter).

     3. Gas recuperation to the decay balloons. (Not possible this year according to the vacuum group.)

* A thin delta-E detector will be installed in the Miniball line to quantify the amount of beam contamination with different Z.

* Updated budget request to be presented to Peter Butler next week.

 

 

Notes by Fredrik Wenander