Minutes from REX integration meeting 7/5/2004

 

Present: Mats Lindroos (chair), Luis Fraile, Pierre Delahaye, Fredrik Wenander, Ivan Podadera

 

 

1. Planning and general issues

* At the next REX meeting Wednesday 12/5, 16:00, the ISOLDE EICs are invited for a discussion about operation, and Ivan Deloose will inform about the control system update.

* The IS399 Li-run has been postponed and will not take place in end of May. Instead a solid state implantation run, using only the RFQ as accelerating element, is scheduled. Praseodymium A=143 is requested as radioactive beam, together with stable Europium (or Cesium as mass marker for beam setting up). A surface ionizer at GPS will be used. Target to be put on the frontend Monday 23/5.

* Two new computers form Leuven operating with Windows 2000 are installed in the control room. All in all we have 4 computers for operation, which should be sufficient.

* The REX workpackage has been updated by Fredrik and sent to Mats Lindroos, Charles Hill and Richard Scrivens.

 

 

2. REXTRAP

* The emittance measurements are still continuing. Efficiencies and emittances for rotating and sideband cooling are studied as function of cooling time, electrode voltage and beam intensity.

* The HV for the REXTRAP caused some sparking last week. The sparks are believed to occur outside the vacuum, and all insulators and the transformer were therefore cleaned again. The reason is unclear, but the sparks are gone for the moment.

* The DDS module (function generator for the trapping elements) was broken and repaired again. Pierre will ask Hegewish in Munich for more ICs of type LH0033CJ.

* The spare ion source has been assembled and a Rhenium liner has been inserted into the graphite oven to enable ionization of Li. The tungsten wires will be exchanged for Re wires. A mass marker with 1000 nA hours Li (10% ionization efficiency included) will be prepared by ISOLDE technical group.

* A brief discussion with Jacques Lettry concerning further developments of the REXTRAP ion source was held. The following conclusion were reached:

1.the Li production should be tried with above described method

2 separate mass marker ovens should be installed

3. possibly use a plasma source (with no gas feeding and small plasma electrode hole)

4. possibly use a source similar to the future ISOLTRAP source which has a built in RF spectrometer for mass separation

* A 500 um Si detector mounted behind an Al-foil has been produced. The detector assembly is mounted on a CF100 flange and will be put after the trap when the emittance measurements are finished. This may improve the radioactive beam identification after the REXTRAP.

 

 

3. REXEBIS and mass separator

* A set of spare parts for the REXEBIS HT 60 kV FuG supply has been ordered for approximately 300 euro.

* The LqHe boil-off rate is still too high. When trying filling Tuesday evening the dewar was almost empty, so the solenoid had to be demagnetized. The solenoid has been refilled on Thursday and ebeam is running again. The Helpdesk at Oxford Instruments has been contacted, but no response received yet.

* Beam injection tests are scheduled for Monday-Tuesday.

* The MCPs in the mass separator were rewired to improve the vacuum and to correct for faulty connections. Four not vacuum tight SHV contacts have been changed for Fisher Lemo connectors.

* The mass separator has been pumped on. The Alcatel vacuum controller for a turbo pumped stopped working. This reoccurring problem will be addressed by David Porret.

* One of the EBIS steerer supplies is under reparation by Nicolas David.

 

 

Notes by Fredrik Wenander