Li run autumn 2005
Target
issues:
* Target number
#309, surface ioniser Mk8, Ta foils
* The Li
current was very sensitive to the line heating. We ran at 330 A on the line.
isotopes run: 9Li2+
breeding time: 3.5 ms for 2+, cooling time 20 ms as the linac
could not operate above 50 Hz
currents: for 11/12 pulses, 1.6E13 p/p
CA0.FC68 = average
6 pA (jumping from 4 to 11 pA)
BTS.FC20 = average
3 pA with 1/3 of Ne
RFQ.FC20 = 0.3 pA
on 9Li2+
efficiency:
*
* TRAP 33% for 20 ms,
very short beam
gate -> some ten pA out, mainly
Li, 10% Ne and a small slow
tail
* EBIS eff 10% for 7Li2+ with 3.5 ms breeding time
With radioactive 9Li2+ around
7.5% (large error bars)
* Trap+EBIS eff 4%
* Linac
transmission and energy: 75% and 2.76 MeV/u
comments:
* Somewhat time inefficient setting
up of the HRS as the separator stood unused for a whole day in total.
* Buffer gas pressure 7 V for Ne.
* Very little (some percent) of
18O4+ in the beam.
* Stripper foils (25
ug/cm2) used to push 9Li2+ into 3+. All beam
went to 3+.
* Tried ion-ion cooling by injecting
He gas into the EBIS. No improvement seen for 7Li+.
technical problems:
* The air conditioning for the RF amplifier room kept
on switching off and as a result the 7-gap cavities stopped due to overheating.
* Difficult to setup the beam transport from HRS to
trap as the HRS separator settings were different from normal settings.
* The HRS NMR probes are not working for 9Li when the
separator is at 30.2 kV, therefore no feedback. Thus we had to cycle the
magnets manually. Fortunately the 9Li could be seen on the scanners and the
magnets be calibrated.
lessons learned:
* Checked with Tim Giles that the NMR probes are
working for 11Li at 30.2 kV in case that beam will be used next year.